The Project Details:
Square Footage: 180,000
Products Installed / Removed: Pallet racking with steel skatewheel carton flow, wire mesh backstops, wire decking. Dismantled around 30,000 sqft. of racking.
Their problem / Our Solution: The customer had a firm deadline for the completion of this project. Storage Solutions had to install runs of racking in one area, then move to another area to install so the customer associates could load the racking and train on picking while we completed the install.
This was an active facility throughout the entire project. SSI install leaders and project managers worked directly with the customer to ensure a fluid transition. This allowed us to keep install moving along efficiently while the customer could also stay up with daily operations. In the end, the project was completed on time 4 days ahead of schedule!